Coal piled up as limping power plant consuming less; authorities may be forced to suspend extraction
With its storage capacity getting almost exhausted with the quantity of 'self-combustible' coal growing, the struggling Barapukuria coal mine may be forced to suspend production on safety grounds, and incur a huge financial loss.
“The mine has a capacity of storing 2,05,000 tonnes of coal as per international safety standard. We already have 2,00,000 tonnes due to a serious reduction of coal consumption by the Barapukuria power plant since late last month,” says a well placed mine source.
The 250 megawatt power plant is the main consumer of the mine's coal. But the plant -- recently taken over by the Power Development Board (PDB) from its Chinese builders and operators-- has drastically slashed coal consumption as it partially went out of order last month. The plant is now generating barely 60 MW power.
“When in full production, the plant consumes 72,000 tonnes of coal. Last month its consumption came down to 38,000 tonnes. This month it would hardly consume 20,000 tonnes,” said the source.
“If this situation goes on, we will have to shut down the mine,” he said, adding that coal is highly self-combustible if certain safety measures are not maintained while storing it.
The mine is currently producing 90,000 - 100,000 tonnes aiming at producing 9,00,000 tonnes within this fiscal year (FY). It also hopes to make its first operating profit this year as its production and sale of coal have been excellent throughout the year (FY).
But the power plant glitch stands as one of the two major hurdles faced by the mine. The other hurdle is a political resistance against mining fuelled by a vested quarter.
A top official of the PDB said experts and technicians from Ghorashal Power Plant have been mobilised to repair the troubled coal-fired power plant's vacuum blower, ID fans, other auxiliary equipment and some other things. There is also a problem with the alignment of some equipment that needs to be addressed.
The PDB also requested Chinese authorities to send some experts to join the repair team.
“We expect the repair to be completed by the end of this month or early next month. But we know repair is not the ultimate solution. Some of the things need replacement, and we have taken initiative to directly purchase quality things from China. It will take three months to have those in hand,” the PDB official said.
Towards the end of the last caretaker government's tenure, the then power secretary had instructed the PDB to develop its own coal yard to ease the pressure on the mine authorities. “We are working on it now,” the official said.
The mine's storage capacity is getting exhausted also because private buyers, who take about 30 percent of the coal, are not buying it right now.
Meanwhile, the mine sold a record 2,30,000 tonnes of coal at $ 111 dollars a tonne to private buyers-- mainly brick kiln owners-- in the current FY. The record sale created prospect of the mine making operating profit for the first time, after incurring more than Tk 150 crore loss in the previous three years of operation.
But this trend of sale stopped last month as brick kilns' “season” is over.
“We could have sold more than 3,00,000 tonnes if the country had communication facilities. We cannot sell coal to consumers in Dhaka region though they are keen to buy our quality coal,” said a miner.
To increase sales, the mining authorities slashed coal price to $96 a tonne, and expect good sales in June-July. This would also help ease the storage situation, he noted.
Our correspondent Kongkon Karmaker adds from Dinajpur: A five-member team of experts from China is now examining technical glitches in Barapukuria power plant.
The experts, who arrived at the plant on Monday and started work next day, looked into the trouble at second unit of the plant, particularly its IDF (induce draft fan).
Plant sources said the second unit would resume operation within a week.
The Chinese team however suggested an extensive overhaul of the unit, a mine official told this correspondent, seeking anonymity.
He also said the team members want another batch of experts from their country to come to the site as they lack the technical know-how and equipment required to do the job they are supposed to.
Earlier, local engineers failed to fix the IDF trouble which was detected on April 21.